PROJECT
Centocor Biopharma
Cork, Ireland
Scope of Works: Commissioning Management
HVAC Test and Balance
Validation of Cleanrooms
Date of Completion:
Duration:
November 2007
17 months
Client: John Sisk & Sons Ltd.    
About This Project...

In 2007 SiBS carried out commissioning and validation on a new 25,000m2 Greenfield Biomedicines Manufacturing facilities

The Facility is arranged around a connecting spine link corridor that unites the following four buildings :

  • Manufacturing including a Class 100,000( ISO 8 ) Cleanroom
  • Laboratory/Administration
  • CUB(central utility building)
  • Warehouse

Through a well delivered commissioning management process, the project was delivered on time and well within cost targets to the client. The facility is one of the safest large scale projects ever constructed in Ireland